Commissioning and handover form
Form code: F-04 Project: …… | Date: …… | Minutes number: ……
4–1. Test information
title | amount |
|---|---|
Employer representative | …… |
Contractor representative | …… |
Mechanical and electrical supervisor | …… |
Delivery operator | …… |
Version of base maps | …… |
Control program version | …… |
Water level during the test | …… |
Weather and wind conditions | …… |
Measuring devices and calibration validation | …… |
Duration of continuous performance test | …… |
4–2. Pre-launch review
row | item | the result | Document number or defect description |
|---|---|---|---|
1 | Matching the installed equipment with the final documents | …… | …… |
2 | Completing the sealing test and fixing the leak | …… | …… |
3 | Washing the circuit and removing the remains of the execution | …… | …… |
4 | Installation and stabilization of pumps, nozzles and lights | …… | …… |
5 | Complete suction protection and accessible vents | …… | …… |
6 | Verification of the status of valves and drain lines | …… | …… |
7 | Completion of electrical inspections and tests | …… | …… |
8 | Availability of water and purification system | …… | …… |
9 | Level control readiness and dry run protection | …… | …… |
10 | Separation of the test area from public attendance | …… | …… |
4–3. Record performance results
equipment or circuit | parameter | Design value and tolerance | Measured value | the result |
|---|---|---|---|---|
pump | Flow Rate | …… | …… | …… |
pump | Pressure or head at defined points | …… | …… | …… |
engine | Current of each phase | …… | …… | …… |
circuit | input power | …… | …… | …… |
nozzle | The height and shape of the effect | …… | …… | …… |
ring | Uniformity of appearance | …… | …… | …… |
Purification | flow rate | …… | …… | …… |
Filter | Initial pressure difference | …… | …… | …… |
the light | Voltage at the place of consumption | …… | …… | …… |
water system | Compensatory water rate in recorded conditions | …… | …… | …… |
4–4. Control tests
scenario | Expected behavior by design | Actual result |
|---|---|---|
Water level drop | …… | …… |
Disconnect control | …… | …… |
Power cut and return | …… | …… |
Emergency stop command | …… | …… |
Over-adjusted wind | …… | …… |
Pump or drive fault | …… | …… |
Interruption of purification circulation | …… | …… |
Departure of water quality from the approved limits, if monitored | …… | …… |
Implementation of the schedule | …… | …… |
Restore application backup | …… | …… |
The error test should be performed with a controlled and verified simulation method; Deliberately creating a dangerous situation in the presence of people is not a test method.
4–5. Documents and items to be delivered
Construction drawing □ Equipment table and serial number □ Operation manual □ Electrical test report □ Mechanical commissioning report □ Maintenance schedule □ Water results □ Control backup □ Management access from secure path □ Spare parts list □ Warranty documents □ Training minutes □
4–6. Defects and delivery decision
defect | Importance | Responsible for fixing | due date | Confirmation certificate |
|---|---|---|---|---|
…… | Safety / functional / appearance | …… | …… | …… |
Status: ready for delivery □ conditional delivery according to the contract □ need to repeat the test □
Defects affecting safety must be fixed and confirmed before allowing public operation.
Contractor's signature: …… Supervisor's signature: …… Employer's signature: …… Operator's signature: ……